Highways update – Llantrisant Road

Plasdwr have today (20/09/2019) provided the following update:

Essential works will be continuing into October, to install BT and drainage services across Llantrisant Road to the new development.  Two-way traffic lights are currently in place from 09:30-15:30 to the west of the filling station to install drainage across the road. From the start of October, we have permission for these lights to be in place 24 hours a day to complete the work. These lights are expected to be in place for approximately two weeks.

We’re sorry for the inconvenience caused, our contractors are working hard to complete this work as quickly as possible.  These timescales are correct at the time of writing. If anything changes, updates will be posted as an update on the Plasdwr website.